Multi-Country ManufacturingHilton Garden Inn Hotels - Case Study
Key Objectives
Reduce overall logistics cost and import tariffs through optimized country-of-origin selection.
Our Approach
1. Multi-Country Manufacturing Strategy
- Brazil handled FF&E fabrication for the Puerto Rico project, benefiting from reduced import tariffs under favorable South American trade routes.
- China managed production for the Costa Rica property, optimizing for material availability and factory specialization in joinery and casegoods.
2. Speed of Execution
Timeline Phase | Duration | Milestone |
Deposit Received | Day 0 | Project kickoff |
Technical Drawings + Material Samples | +5 Days | Delivered for review |
Client Approvals | +7 Days | Drawings & finishes approved |
Production | +35 Days | Full FF&E fabrication completed |
Total Project Duration | <45 Days | Delivery ready for export |
3. Material Optimization & Brand Compliance
- Casegoods: RH-grade wood substrates, high-pressure laminates, and contract finishes tested for durability.
- Metalwork: Powder-coated and anodized finishes to match brand specifications.
- Upholstery: High-performance textiles compliant with HGI flame and wear standards.
4. Logistics Coordination & Tariff Savings
- Brazil → Puerto Rico: Avoided significant ocean freight delays and reduced tariffs by nearly 30% compared to Asian sourcing.
- China → Costa Rica: Leveraged established export infrastructure, enabling faster customs clearance and competitive freight rates.
Key Success Factors & Results
- Dual-country manufacturing model optimized logistics and tariffs while preserving quality.
- Accelerated approval and production cycle enabled full delivery within 45 days of deposit.
- Strong vendor coordination ensured simultaneous progress across international factories.
- End-to-end project management maintained alignment with Hilton’s design and operational standards
Metric | Brazil → Puerto Rico | China → Costa Rica |
Production Lead Time | 40 days | 43 days |
Tariff Savings | ~30% | ~22% |
Transit Time | Reduced by 18 days | Reduced by 15 days |
Quality Compliance | 100% Hilton-approved | 100% Hilton-approved |
Overall Schedule Adherence | On time | On time |